TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting challenges, including extremely tight access and a high water table.

The east elevator pit was constructed with a 10 m deep caisson wall, braced horizontally against the existing subway structure. Piles were drilled with a Bauer BG 22H self-lining drill in order to overcome the high groundwater conditions.

The west elevator pit was constructed with an 8 m deep lagging wall, the piles for which were drilled in a single weekend in order to comply with TTC and City of Toronto access restrictions. HC Matcon’s excavation operations were aided by our own dewatering systems installed at each elevator pit. A total of 4 deep wells were effectively used to lower the water table below final excavation grade.

Client: Consolidated Canadian
Location: Toronto, Ontario

Currie Barracks Residential Development

Currie Barracks Residential Development HCM was contracted to provide the design and installation of shoring system for a multi-family condo development in the Currie Barracks area SW Calgary. Conventional cantilever
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More

Maxwell Bates

Maxwell Bates This project, located on Fourth Street in the downtown core of Calgary, consisted of a tied-back continuous caisson wall.  The caisson wall provided zero ground loss and minimal
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More