Complex Shoring Requires Innovative Design

Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete shoring systems.

  • Shoring designs were required to incorporate work next to the existing CN passenger rail tracks and the historical heritage buildings being developed into the new structure design.
  • Due to the nature and age of the buildings impacted by the work shoring design required flexibility of design while maintaining and adhering to the strict tolerances required by the specifications.

The combination of the shoring systems in conjunction with the design capacity for on site modifications allowed the excavation to be completed uniformly across the site and helped to accelerate the construction schedule.

Client: Urbacon Ltd
Location: Guelph, Ontario

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for