Skip to content

Odeon Ronmore Development

Odeon Ronmore Development

HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area SW Calgary. RWH designed a tied-back pile and timber lagging shoring system to support the vertical excavation for the foundation wall along the majority of the building perimeter. Due to overhead power restrictions and minimal clearances to the property line, the laneway side of the project was supported by a soil nailed shotcrete system. The laneway shoring presented various challenges including anchor encroachment limitations that could not exceed 6.0m to the adjacent property. Anchors were tightly spaced and injection grouted bars installed to gain increased soil adhesion. Regular site inspections and monitoring was performed by RWH to review the performance of the shoring and confirm the design during all stages of the excavation. The shoring was designed for a maximum excavation depth of 10m below grade for a total of 13,200 SF of shoring area.

HCM finished this project on schedule working with the General Contractor to escalate excavation activities and meet the occupancy milestone outlined by the owner.

Location: Calgary, Alberta

Customer: Chandos Construction Ltd.

University of Toronto Faculty of Law

TTC Steels Launch Shaft The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Bluwater Condominiums

Bluwater Condominiums

The Pemberton Group is adding the luxury waterfront Bluwater Condominiums to its portfolio. The 22,000 SF area of shoring area will accommodate the construction of three eight-story buildings on the
Read More