Herald Block

Herald Block

HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation spanned a city block and extended 22 meters deep. The shoring system, designed by RWH Engineering Inc. (RWH), was comprised of an 11 meter deep perched caisson wall above shotcrete, which continued into the rock for the remaining depth of the excavation. 

The challenges faced on this project included old foundations encountered during drilling, surrounding tightly clustered utilities, vulnerable neighbouring structures, and the adjacent light rail transit (LRT) system. HCM met these challenges with close attention to detail and meticulous planning to prevent any utility conflicts and structural damage. RWH completed the precision monitoring of the shoring and adjacent structures providing weekly reports to all stakeholders for the duration of the project. 

Client: EllisDon Corporation

Location: Calgary, Alberta

HCM was able to use their experience on past projects to design and construct a shoring solution that worked with the varying soil conditions at depth. This solution resulted in a more sustainable project as the perched wall required less material than a traditional full depth caisson wall, and provided project cost and schedule savings. Brookfield Place is an example of the ability of the HC Group to work together and overcome challenges in complex projects.

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More