The Osterberg Cell

The Osterberg Cell

HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close proximity to the City Hall. The outcome of the load test was to determine the actual soil parameters for the foundation pile design on the project.

The O-cell is a hydraulically driven, high capacity, sacrificial loading device installed within the foundation unit. As the load is applied to the O cell, it begins working in two directions; upward against upper side shear and downward against base resistance and lower side shear (if applicable). Each O-cell is specially instrumented to allow for direct measurement of the O-cell’s expansion. O-cells range in capacities from 800 kN to 26,000 kN.

The scope of work consisted in installation of single test pile (1070mm diam. x 8.0 meters top liner casing, 910mm diam. x 8.0 meters rock socket). The overall length of test pile was approx.16 meters. O-cell was attached to the bottom of the steel frame c/w instrumentation connections, gauges, wiring etc.

Steel frame was manufactured in HCM’s shop, the O-cell was supplied by Loadtest Inc. HCM installed the pile in one day according to the timeline and specification requirements.

Client: Tetra Tech EBA

Location: Calgary, Alberta

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More
Bluwater Condominiums

Bluwater Condominiums

The Pemberton Group is adding the luxury waterfront Bluwater Condominiums to its portfolio. The 22,000 SF area of shoring area will accommodate the construction of three eight-story buildings on the
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More