Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem

Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment.

  • Due to the tight confines of the site and the proximity of exterior walls, columns and footings, the use of a traditional soldier pile and lagging system was not feasible.
  • Instead, a shotcrete shoring and underpinning solution was developed in conjunction with the Owner and the General Contractor.
  • By working with the forming contractor, a zero clearance solution was used as the backside of the new form work.
  • In addition to vertical cut stability, the shotcrete was also designed to provide underpinning stabilization to the undermined column pad footings and exterior wall footings.
  • By placing strategically located vertical mini piles at and around the pad footings, the additional stabilization was achieved.

The use of the shotcrete solution in this application allowed the General Contractor to minimize disturbance and disruption to the ongoing facility operations.

Client: Stucor Construction Ltd
Location: Niagara Falls, Ontario

HC Matcon - Twinning of the West Trunk Sanitary Sewer

Twinning of the West Trunk Sanitary Sewer

Twinning Of The West Trunk Sanitary Sewer This project includes the installation of a deep trunk sanitary sewer within bedrock under Erin Mills Parkway in Mississauga. HCM together with RWH Engineering
Read More

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More

Talbot Street

Talbot Street HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More

Highland Creek WWTP

Highland Creek WWTP Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More