Skip to content

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem

Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment.

  • Due to the tight confines of the site and the proximity of exterior walls, columns and footings, the use of a traditional soldier pile and lagging system was not feasible.
  • Instead, a shotcrete shoring and underpinning solution was developed in conjunction with the Owner and the General Contractor.
  • By working with the forming contractor, a zero clearance solution was used as the backside of the new form work.
  • In addition to vertical cut stability, the shotcrete was also designed to provide underpinning stabilization to the undermined column pad footings and exterior wall footings.
  • By placing strategically located vertical mini piles at and around the pad footings, the additional stabilization was achieved.

The use of the shotcrete solution in this application allowed the General Contractor to minimize disturbance and disruption to the ongoing facility operations.

Client: Stucor Construction Ltd
Location: Niagara Falls, Ontario

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More

Oshawa Mall

Oshawa Mall The Oshawa Mall expansion was a large project that required several foundation and shoring services. HCM met the needs of the contractor by providing both tied back and
Read More
Bluwater Condominiums

Bluwater Condominiums

The Pemberton Group is adding the luxury waterfront Bluwater Condominiums to its portfolio. The 22,000 SF area of shoring area will accommodate the construction of three eight-story buildings on the
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More