TTC St. Clair Station

Overcoming Tight Access and High Water Table

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted with some interesting challenges, including extremely tight access and a high water table.

  • The east elevator pit was constructed with a 10 m deep caisson wall, braced horizontally against the existing subway structure. Piles were drilled with a Bauer BG 22H self-lining drill in order to overcome the high groundwater conditions.
  • The west elevator pit was constructed with an 8 m deep lagging wall, the piles for which were drilled in a single weekend in order to comply with TTC and City of Toronto access restrictions.
  • HC Matcon’s excavation operations were aided by our own dewatering systems installed at each elevator pit.
  • A total of 4 deep wells were effectively used to lower the water table below final excavation grade.

Client: Consolidated Canadian

Location: Toronto, Ontario

TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More

Herald Block

Herald Block HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM)
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More