Aldershot GO Station Improvements

Our Innovative Solution Saves Time

Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The project was further complicated by the proximity of high speed passenger train rails and the need to maintain and operate the facility while the work was in progress.

  • In order to minimize the impact of the installation of the shoring, HC Matcon Inc. opted to install a single row of multi-strand high capacity tie backs; in excess of 900 KN capacities.
  • The high design loads required these anchors installed under strict on site quality control of strand and grouting procedures.

The innovative approach taken by HC Matcon Inc’s design team provided the optimum solution to the strict requirements of the project while, significantly reducing the duration and subsequent impact to the overall project completion schedule.

Client: Kenaidian Contracting
Location: Burlington, Ontario

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More