The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking.

HC Matcon was responsible for:

  •  installing the approximately 20,000 square feet of zero clearance shotcrete and caisson wall to be used as a back form for the foundation walls.
  • 121 caissons to support the foundation perimeter and new ambulance bay canopy drilled with a Watson 3110.

HC Matcon’s alternative shotcrete shoring solution added value to the project with a substantial cost savings to the owner.

Client: Harbridge and Cross
Location: Toronto, Ontario

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More

Odeon Ronmore Development

Odeon Ronmore Development HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts