Currie Reservoir

Horizontal Underpinning

This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary. The interlocking secant pile wall (caisson wall) allows for an accelerated construction schedule as it eliminates the ground loss that is present with the use of other styles of shoring. Where utilities were present, bracing supports were used to resist the lateral pressures present behind the filler piles.

Unique to this job was the installation of horizontal underpinning. The job required a new connection between the existing reservoir and pump house. To accomplish this task, a tunnel had to be created to accommodate the 900mm connecting water pipe. The underpinning provides support for the tunnel walls. The system worked well; after excavation, the resulting tunnel allowed safe access for the installation of the connection pipe to the pump house.

Because of the job’s proximity to the working water reservoir, special environmental precautions had to be taken in order to avoid contamination. Site-specific procedures were implemented; in instances where lubricating oils had to be used, for example when sliding the horizontal underpinning beams, food grade oils were used over hydrocarbon-based oils. As a result, the integrity of the water supply was maintained throughout the duration of the project.

Client: PCL
Location: Calgary, Alberta

Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More