Skip to content

Currie Reservoir

Horizontal Underpinning

This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary. The interlocking secant pile wall (caisson wall) allows for an accelerated construction schedule as it eliminates the ground loss that is present with the use of other styles of shoring. Where utilities were present, bracing supports were used to resist the lateral pressures present behind the filler piles.

Unique to this job was the installation of horizontal underpinning. The job required a new connection between the existing reservoir and pump house. To accomplish this task, a tunnel had to be created to accommodate the 900mm connecting water pipe. The underpinning provides support for the tunnel walls. The system worked well; after excavation, the resulting tunnel allowed safe access for the installation of the connection pipe to the pump house.

Because of the job’s proximity to the working water reservoir, special environmental precautions had to be taken in order to avoid contamination. Site-specific procedures were implemented; in instances where lubricating oils had to be used, for example when sliding the horizontal underpinning beams, food grade oils were used over hydrocarbon-based oils. As a result, the integrity of the water supply was maintained throughout the duration of the project.

Client: PCL
Location: Calgary, Alberta

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More

McMaster Nuclear Building

McMaster Nuclear Building The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines