Highland Creek WWTP

Highland Creek WWTP

Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the residents of Scarborough.  HC Matcon was procured to install several excavation support walls within the treatment plant.

HC Matcon installed seventy-four soldier piles along with multiple tiebacks and shotcrete.  Due to the proximity of the proposed addition, the underground utilities posed a challenging concern.  To avoid disruption and contact with the existing utilities, HC Matcon implemented a perched pile system.  HC Matcon also designed a shoring system around the underground utilities and allowed work to proceed.

HC Matcon completed all work as per industry details combined with innovative connection designs which were incorporated to save schedule time.

Client: Alberici Constructors Inc.

Location: Scarborough, Ontario

Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More

Odeon Ronmore Development

Odeon Ronmore Development HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More