CN Malton GO Station

Challenge: Build While Trains Are Running

Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.

HC Matcon’s scope of work, includes:

  • 37 caissons at 30-inch diameter, and an approximately 25-foot deep shoring system with strand anchors.
  • The pile and caisson installation was challenging due to a number of factors. The train tracks, in close proximity to the work being done, were required to be fully operational.
  • Special precautions were taken for track protection and the safety of workers.
  • Due to the close proximity to Pearson International Airport, special precautions were taken to conform to the Greater Toronto Airport Authority’s guidelines for the operation of high-mast drills and cranes.
  • HC Matcon accommodated special staging requirements set forth by CN for work, such as the installation of the precast tunnel and track relocations.

HC Matcon will work with all parties involved in a project to ensure a swift execution with minimal conflicts.

Client: B. Gottardo
Location: Toronto, Ontario

Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More

Oshawa Mall

Oshawa Mall The Oshawa Mall expansion was a large project that required several foundation and shoring services. HCM met the needs of the contractor by providing both tied back and
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More