Canada Post Micropiles

No Emissions, No Problem

The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As the project was undertaken in an active mail processing facility, the execution presented a number of challenges. Due to the nature of the building, HCM had to deal with limited access and low overhead clearance.

Notably, there was a requirement that forbade any emissions within the building from operating equipment. This resulted in restrictions on the mobilizing of equipment, where fuel-powered engines could not be used. To solve this problem, the equipment was moved into place using an electric forklift. To satisfy the zero emission policy during work, a ducting system was conceived that vented the exhaust from the operating machines to the outside air via a connection through the roof of the building.

The nature of the facility also meant that work had to be conducted on weekends, when operations at the mail facility are light. HCM’s crew had to abide by security restrictions which limited access to specific parts of the building.

Despite the challenges, the project went well with HCM’s scope of work being completed in two days. To achieve the required capacity of the micropiles, post-grouting was required. Seven days after the installation, the piles were load tested to 150%.

Client: Scott Builders
Location: Calgary, Alberta

Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More

TTC Patten Building

TTC Patten Building HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More

Midtown Lofts

Midtown Lofts On this project, HCM in conjunction with RWH Engineering Inc. (RWH), provided the owner with a complete design-build package and precision monitoring services for an 8.5m deep temporary
Read More