Canada Post Micropiles

No Emissions, No Problem

The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As the project was undertaken in an active mail processing facility, the execution presented a number of challenges. Due to the nature of the building, HCM had to deal with limited access and low overhead clearance.

Notably, there was a requirement that forbade any emissions within the building from operating equipment. This resulted in restrictions on the mobilizing of equipment, where fuel-powered engines could not be used. To solve this problem, the equipment was moved into place using an electric forklift. To satisfy the zero emission policy during work, a ducting system was conceived that vented the exhaust from the operating machines to the outside air via a connection through the roof of the building.

The nature of the facility also meant that work had to be conducted on weekends, when operations at the mail facility are light. HCM’s crew had to abide by security restrictions which limited access to specific parts of the building.

Despite the challenges, the project went well with HCM’s scope of work being completed in two days. To achieve the required capacity of the micropiles, post-grouting was required. Seven days after the installation, the piles were load tested to 150%.

Client: Scott Builders
Location: Calgary, Alberta

Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More