During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo. HCM was retained by Mady Developments to design, supply, and install a complete 9,500 SF bypass shotcrete shoring system.

RWH Engineering Inc. (RWH), an HC Group company, took on the design and monitoring responsibility for the project. The design consisted of a tied-back bypass shotcrete shoring system to a depth of approximately 5 meters. Bypass shotcrete is a unique solution developed by HCM which combines the benefits of shotcrete with a traditional piling system.

HCM’s design-build approach allows for a single source of responsibility. The HCM/RWH integrated working relationship facilitates quick response to design changes and site issues that may occur, ultimately minimizing potential delays and helping to maintain project milestones.

Client: Mady Development Construction Ltd.

Location: Waterloo, Ontario

The HC Group team is positioned to provide exemplary service when performing design-build work – providing both cost and schedule savings to the project.

Currie Barracks Residential Development

Currie Barracks Residential Development HCM was contracted to provide the design and installation of shoring system for a multi-family condo development in the Currie Barracks area SW Calgary. Conventional cantilever
Read More

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More

Lakeview Water Treatment Plant

Lakeview Water Treatment Plant This project was part of the second phase of an expansion program to the region of Peel’s Lakeview Water Treatment Plant. Given the information provided at
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During