Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th Street SW, Calgary, Alberta. Centron, a developer, decided to buy it and changed the concept to a single building, mixed-use office retail development. The site was already excavated and seven levels of underground parking completed so a considerable amount of structural redesign was necessary; which includes the upgrade on the existing foundation system.

Designed by RWH Engineering, 80 micropiles are installed 20 to 30 feet below the existing footing to support the additional load. As the installation was undertaken in a 7th floor underground parkade, HCM had to deal with limited access and low overhead clearance. Man-portable drilling equipment was used to compile with these limitations.

Despite the challenges, the project went well with HCM scope of work being completed on schedule. The pile capacity is confirmed by one verification test and five proof tests.

Client: Centron
Location: Calgary, Alberta

TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Credit Valley Hospital

Credit Valley Hospital

Alternative to Save Time and Money The Credit Valley Hospital in Mississauga, Ontario is undergoing a massive expansion and renovation. HC Matcon was brought in to undertake the shoring, underpinning,
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More