Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th Street SW, Calgary, Alberta. Centron, a developer, decided to buy it and changed the concept to a single building, mixed-use office retail development. The site was already excavated and seven levels of underground parking completed so a considerable amount of structural redesign was necessary; which includes the upgrade on the existing foundation system.

Designed by RWH Engineering, 80 micropiles are installed 20 to 30 feet below the existing footing to support the additional load. As the installation was undertaken in a 7th floor underground parkade, HCM had to deal with limited access and low overhead clearance. Man-portable drilling equipment was used to compile with these limitations.

Despite the challenges, the project went well with HCM scope of work being completed on schedule. The pile capacity is confirmed by one verification test and five proof tests.

Client: Centron
Location: Calgary, Alberta

Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario