Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th Street SW, Calgary, Alberta. Centron, a developer, decided to buy it and changed the concept to a single building, mixed-use office retail development. The site was already excavated and seven levels of underground parking completed so a considerable amount of structural redesign was necessary; which includes the upgrade on the existing foundation system.

Designed by RWH Engineering, 80 micropiles are installed 20 to 30 feet below the existing footing to support the additional load. As the installation was undertaken in a 7th floor underground parkade, HCM had to deal with limited access and low overhead clearance. Man-portable drilling equipment was used to compile with these limitations.

Despite the challenges, the project went well with HCM scope of work being completed on schedule. The pile capacity is confirmed by one verification test and five proof tests.

Client: Centron
Location: Calgary, Alberta

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More

Maxwell Bates

Maxwell Bates This project, located on Fourth Street in the downtown core of Calgary, consisted of a tied-back continuous caisson wall.  The caisson wall provided zero ground loss and minimal
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen