Centre 10

Centre 10

Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th Street SW, Calgary, Alberta. Centron, a developer, decided to buy it and changed the concept to a single building, mixed-use office retail development. The site was already excavated and seven levels of underground parking completed so a considerable amount of structural redesign was necessary; which includes the upgrade on the existing foundation system.

Designed by RWH Engineering, 80 micropiles are installed 20 to 30 feet below the existing footing to support the additional load. As the installation was undertaken in a 7th floor underground parkade, HCM had to deal with limited access and low overhead clearance. Man-portable drilling equipment was used to compile with these limitations.

Despite the challenges, the project went well with HCM scope of work being completed on schedule. The pile capacity is confirmed by one verification test and five proof tests.

Client: Centron
Location: Calgary, Alberta

Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More

Currie Barracks Residential Development

Currie Barracks Residential Development HCM was contracted to provide the design and installation of shoring system for a multi-family condo development in the Currie Barracks area SW Calgary. Conventional cantilever
Read More

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More