Skip to content

University of Ottawa STEM Complex

University of Ottawa STEM Complex

HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh Ottawa winter, HCM deployed double crews, 24 hours a day for both vertical drilling and anchor installation. Constant adaptation to the soil conditions was needed due to the presence of soft clays, cobbley till, and flowing sands. Multiple freeze-thaw cycles made for challenging site conditions requiring proficient site communication to ensure a productive and safe jobsite. RWH Engineering Inc. produced an efficient shoring solution and by self-performing the precision monitoring allowed for the design to be verified closely with the excavation procedures. In-house engineering support also ensured there was no downtime caused by unforeseen conditions or site issues.

HCM worked alongside the other contractors to expedite the project to the bottom of the 17 meter deep site in 3 months.

Location: Ottawa, Ontario

Customer: R.W. Tomlinson Ltd

TTC Patten Building

TTC Patten Building HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More