Skip to content

Burke Residence

Burke Residence

The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley portion of the site. The site was located in the Elboya Park region of SW Calgary. The purpose of the shoring was to protect the adjacent neighbouring property and utilities along the east, west and back sides of the site.

The east and the west sides of the property were shored with a cantilever steel pipe and timber lagging system. The shoring on these sides extended to 11 feet below grade, and approximately 70 feet long for a total area of 1,800 square feet.

The back side of the property presented the greatest challenge as it was along the steepest slope of the site with a designed depth of 15 feet below grade. Due to the site conditions, shotcrete was an ideal shoring solution. The total area of the shotcrete shoring covered 350 square feet.

Due to the residential nature of the site special emphasis was put on the impact of the project to the surrounding area. The disruption to neighbouring properties, along with noise and vibration and existing structures was carefully monitored and managed.

HCM finished the project on schedule completing in two planned stages according to the progress requirements of the general contractor.

Client: Hillson Homes

Location: Calgary, Alberta

St. Joseph's Healthcare Redevelopment Project

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More

Herald Block

Herald Block HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation
Read More
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More