Skip to content

Smith Residence

Toronto’s First Permanent Soil Nail Wall

This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in Toronto.

  • Micro piles were used to support a cantilever canopy on one level and HC Matcon completed the full excavation, shoring and footings as a package to the owner.
  • The shoring design called for over sized MAI bars due to low corrosive soil, and a 100 year plus life is expected.
  • The house construction is wood framed which was a lower cost than steel/concrete in that hillside loads over time are taken by the shoring system, which is 150 mm from the house walls.
  • The advantages of shotcrete shoring include smaller equipment to access and do the nails, as typical shoring solution involved large equipment and high costs to build working berms on a hillside lot.

Owners of land that was typically considered unsuitable as building lots can re consider and realize hidden value with permanent soil nail walls constructed by HC Matcon. HCM is a full service Design Build Specialist contractor.

Client: HC Matcon
Location: Toronto, Ontario

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More

Highland Creek WWTP

Highland Creek WWTP Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More