EEEL University of Calgary

Zero Ground Loss

This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for the foundations were almost identical to the previous project, with the installation of approximately 175 cast-in-place belled piles. Again, this new building was a result of the fast-growing population at the University of Calgary and the demand for specialty studies with emphasis on future global trends such as clean energy and the environment.

The soil conditions, which are typical and uniform throughout the mentioned site, consisted mainly of silty sand and clay till which is ideal for large capacity belled piles.

  • The shafts for the piles were predominantly 900mm, 1000mm, and 1,200mm in diameter.
  • The bells were sized at: 2000mm, 2400mm, 2800mm, 3400mm and 3600mm in diameter.

The average founding depth on this project was approximately 13.0m – 17.0m with the need to protect the upper portion of the pile shafts by using temporary casing approximately 8.0m long. The concrete volumes for single piles ranged between 23 – 26 cubic meters. Among the challenges for HCM on this project was installation of piles in close proximity to a concrete utility tunnel. EllisDon approached HCM with a request for shoring and underpinning on a portion of the tunnel.

HCM proposed a design/build tied-back continuous caisson wall method where special consideration was given to the stated goal of zero ground loss from underneath of the tunnel.

Client: EllisDon Corporation
Location: Calgary, Alberta

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More