EEEL University of Calgary

Zero Ground Loss

This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for the foundations were almost identical to the previous project, with the installation of approximately 175 cast-in-place belled piles. Again, this new building was a result of the fast-growing population at the University of Calgary and the demand for specialty studies with emphasis on future global trends such as clean energy and the environment.

The soil conditions, which are typical and uniform throughout the mentioned site, consisted mainly of silty sand and clay till which is ideal for large capacity belled piles.

  • The shafts for the piles were predominantly 900mm, 1000mm, and 1,200mm in diameter.
  • The bells were sized at: 2000mm, 2400mm, 2800mm, 3400mm and 3600mm in diameter.

The average founding depth on this project was approximately 13.0m – 17.0m with the need to protect the upper portion of the pile shafts by using temporary casing approximately 8.0m long. The concrete volumes for single piles ranged between 23 – 26 cubic meters. Among the challenges for HCM on this project was installation of piles in close proximity to a concrete utility tunnel. EllisDon approached HCM with a request for shoring and underpinning on a portion of the tunnel.

HCM proposed a design/build tied-back continuous caisson wall method where special consideration was given to the stated goal of zero ground loss from underneath of the tunnel.

Client: EllisDon Corporation
Location: Calgary, Alberta

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More

Cobourg Railway Station

Cobourg Railway Station On this project, HCM, in conjunction with its in-house engineering company, RWH Engineering Inc. (RWH), was able to offer the owner one source for the design, supply,
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More