HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets and when TTC transitioned to using tokens the increased loading caused settlement and structural issues which required strengthening of its foundations. 

The project consisted of drilling and installing 90 micropiles to a depth of 15M.  Working conditions presented an issue as drilling was restricted in a basement of an existing building where headroom was 3.5 meters high. HCM mobilized the Klemm low headroom drill rig in order to complete the project with productions to meet the strict deadlines required from TTC. 

The project was completed in a timely fashion and on budget. HC Matcon is well equipped to deal with difficult conditions presented on any project and are experts in micropile installations.

Client: Toronto Transit Commission & Buttcon LTD.

Location: Toronto, Ontario

Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More

McMaster Nuclear Building

McMaster Nuclear Building The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More