Skip to content

Burke Residence

Burke Residence

The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley portion of the site. The site was located in the Elboya Park region of SW Calgary. The purpose of the shoring was to protect the adjacent neighbouring property and utilities along the east, west and back sides of the site.

The east and the west sides of the property were shored with a cantilever steel pipe and timber lagging system. The shoring on these sides extended to 11 feet below grade, and approximately 70 feet long for a total area of 1,800 square feet.

The back side of the property presented the greatest challenge as it was along the steepest slope of the site with a designed depth of 15 feet below grade. Due to the site conditions, shotcrete was an ideal shoring solution. The total area of the shotcrete shoring covered 350 square feet.

Due to the residential nature of the site special emphasis was put on the impact of the project to the surrounding area. The disruption to neighbouring properties, along with noise and vibration and existing structures was carefully monitored and managed.

HCM finished the project on schedule completing in two planned stages according to the progress requirements of the general contractor.

Client: Hillson Homes

Location: Calgary, Alberta

Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More