Skip to content

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used soldier piles and shotcrete lagging shoring (SPLS) with soil nails to support the excavation of an approximately 30-foot deep underground parking garage.

One challenge of this project was the close proximity of the excavation to the property line of the adjacent residential buildings. The consultant’s design included a caisson wall for this part of the system. HC Matcon proposed an alternative to save the owner and general contractor money, schedule time, and square footage of finished building by applying an equivalent system of shotcrete shoring and soil nails. This system will also act as a one-sided form for foundation walls.

During this project, there were some unforeseen obstacles for the shoring installation that required avoidance.

Utilities were found between the shoring system and the adjacent existing building footings to be demolished. HC Matcon was able to modify the pile design to support these utilities during demolition.


Other concrete obstructions were avoided by using an alternative pipe pile design to satisfy property line constraints, a perched walkway for the access of neighboring houses, and to facilitate the demolition of the existing parking garage.

HC Matcon will take on many challenges related to shoring and foundation design while keeping the interests of the general contractor and owner in mind.

Client: Lewis Build Corporation
Location: Toronto, Ontario

Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More