CN Malton GO Station

Challenge: Build While Trains Are Running

Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.

HC Matcon’s scope of work, includes:

  • 37 caissons at 30-inch diameter, and an approximately 25-foot deep shoring system with strand anchors.
  • The pile and caisson installation was challenging due to a number of factors. The train tracks, in close proximity to the work being done, were required to be fully operational.
  • Special precautions were taken for track protection and the safety of workers.
  • Due to the close proximity to Pearson International Airport, special precautions were taken to conform to the Greater Toronto Airport Authority’s guidelines for the operation of high-mast drills and cranes.
  • HC Matcon accommodated special staging requirements set forth by CN for work, such as the installation of the precast tunnel and track relocations.

HC Matcon will work with all parties involved in a project to ensure a swift execution with minimal conflicts.

Client: B. Gottardo
Location: Toronto, Ontario

Brantford General Hospital

Brantford General Hospital This innovative project represents the first use of shotcrete shoring in place of caisson walls against a building in Ontario. Caisson walls have typically been utilized duw
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a