CN Malton GO Station

Challenge: Build While Trains Are Running

Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.

HC Matcon’s scope of work, includes:

  • 37 caissons at 30-inch diameter, and an approximately 25-foot deep shoring system with strand anchors.
  • The pile and caisson installation was challenging due to a number of factors. The train tracks, in close proximity to the work being done, were required to be fully operational.
  • Special precautions were taken for track protection and the safety of workers.
  • Due to the close proximity to Pearson International Airport, special precautions were taken to conform to the Greater Toronto Airport Authority’s guidelines for the operation of high-mast drills and cranes.
  • HC Matcon accommodated special staging requirements set forth by CN for work, such as the installation of the precast tunnel and track relocations.

HC Matcon will work with all parties involved in a project to ensure a swift execution with minimal conflicts.

Client: B. Gottardo
Location: Toronto, Ontario

Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More

Odeon Ronmore Development

Odeon Ronmore Development HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More