Centron Business Park Retaining Wall

Steep Slope Retaining Wall

The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast Calgary, Alberta. The purpose of the permanent wall was to support a portion of 4th Street S.E. which is serving as an access road to a multi-building complex for commercial real estate. The retaining wall was designed by EBA Engineering Consultants Ltd. as a Cantilever Tangent Wall with various excavation depths, c/w embedment of soldier piles between 7.5m and 14.5m below-grade. The length of shoring wall was 142 linear metres with a total of 470 square metres of exposed surface area. The pile sizes included diameters of 810mm and 912mm. The overall scope of work consisted of drilling approximately 70 soldier piles and 140 filler piles. The client also accepted HCM’s proposal to trim the front surface of the 10 MPa concrete wall which then became more suitable for future application of architectural cladding or finished shotcrete. HCM completed this task with an excavator-mounted Antraquip wall trimmer.

The design also required precision in the placing of the piles along the contour of a curvilinear access road which, in most cases, took place on the edge of a steep slope.

HCM Contractors successfully completed this project to the engineer’s satisfaction, and on schedule.

Client: Centron Group of Companies
Location: Calgary, Alberta

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both