St. Thomas Courthouse

Alternate Methods Stop Running Sands

HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction of the proposed shoring was initially for soldier piles and lagging with a single level of bracing using tiebacks.

The existing structures were initially designed using conventional underpinning. When excavation reached the underside of the existing structures it had been determined that soils were not what expected in the geotechnical report. The existing soil conditions were flowing wet sands and HCM was asked to provide an alternate method to the conventional underpinning.

HCM implemented a shotcrete underpinning system including positive support of the existing rubble foundation to allow us to support the structure and lateral pressure of the earth while excavation proceeded to base of the new structure.

With the assistance of RWH (an HC Group of companies) our ability to react and provide an alternate design solution allowed HCM to complete successfully the shoring and foundation works within EllisDon’s budget and schedule.

Client: EllisDon Construction
Location: St. Thomas, Ontario

St. Thomas Courthouse - Shotcrete, Soldier Piles & Lagging

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More

TTC Patten Building

TTC Patten Building HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh