The Osterberg Cell

The Osterberg Cell

HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close proximity to the City Hall. The outcome of the load test was to determine the actual soil parameters for the foundation pile design on the project.

The O-cell is a hydraulically driven, high capacity, sacrificial loading device installed within the foundation unit. As the load is applied to the O cell, it begins working in two directions; upward against upper side shear and downward against base resistance and lower side shear (if applicable). Each O-cell is specially instrumented to allow for direct measurement of the O-cell’s expansion. O-cells range in capacities from 800 kN to 26,000 kN.

The scope of work consisted in installation of single test pile (1070mm diam. x 8.0 meters top liner casing, 910mm diam. x 8.0 meters rock socket). The overall length of test pile was approx.16 meters. O-cell was attached to the bottom of the steel frame c/w instrumentation connections, gauges, wiring etc.

Steel frame was manufactured in HCM’s shop, the O-cell was supplied by Loadtest Inc. HCM installed the pile in one day according to the timeline and specification requirements.

Client: Tetra Tech EBA

Location: Calgary, Alberta

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More