The Osterberg Cell

The Osterberg Cell

HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close proximity to the City Hall. The outcome of the load test was to determine the actual soil parameters for the foundation pile design on the project.

The O-cell is a hydraulically driven, high capacity, sacrificial loading device installed within the foundation unit. As the load is applied to the O cell, it begins working in two directions; upward against upper side shear and downward against base resistance and lower side shear (if applicable). Each O-cell is specially instrumented to allow for direct measurement of the O-cell’s expansion. O-cells range in capacities from 800 kN to 26,000 kN.

The scope of work consisted in installation of single test pile (1070mm diam. x 8.0 meters top liner casing, 910mm diam. x 8.0 meters rock socket). The overall length of test pile was approx.16 meters. O-cell was attached to the bottom of the steel frame c/w instrumentation connections, gauges, wiring etc.

Steel frame was manufactured in HCM’s shop, the O-cell was supplied by Loadtest Inc. HCM installed the pile in one day according to the timeline and specification requirements.

Client: Tetra Tech EBA

Location: Calgary, Alberta

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More

McMaster Nuclear Building

McMaster Nuclear Building The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More