HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was installed for the construction of a two storey underground parking structure.

A combination of tiebacks and internal struts were used to support the 12.0m deep excavation. After piling was complete tieback encroachment became no longer possible along the west wall and had to be converted to a double rakered system. As the foundation structure was entirely precast this presented unique challenges when using rakers. RWH worked together with HCM and the Developer to make the internal bracing system work around the precast panels and designed the system to allow for removals to help facilitate the constriction process.

The shoring was constructed next to an existing church sensitive to movements. Excavation procedures were modified and extra considerations were taken in both the design and construction to reduce any movements and vibrations. Further, RWH completed target, inclinometer and vibration monitoring to verify the shoring performance throughout construction and ensure minimal impact to the church structure.

Client: The Tricar Group

Location: London, Ontario

Aligning with the HCM group’s core value of sustainability, the Azure project became the first LEEDS condominium project in London’s history.

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
Credit Valley Hospital

Credit Valley Hospital

Alternative to Save Time and Money The Credit Valley Hospital in Mississauga, Ontario is undergoing a massive expansion and renovation. HC Matcon was brought in to undertake the shoring, underpinning,
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More

Highland Creek WWTP

Highland Creek WWTP Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Grand House

Grand House

Difficult But Not Impossible The Grand House is a student designed and constructed co-operative housing project located in Cambridge, Ontario.  It has won awards and is a landmark building. Due
Read More