HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was installed for the construction of a two storey underground parking structure.

A combination of tiebacks and internal struts were used to support the 12.0m deep excavation. After piling was complete tieback encroachment became no longer possible along the west wall and had to be converted to a double rakered system. As the foundation structure was entirely precast this presented unique challenges when using rakers. RWH worked together with HCM and the Developer to make the internal bracing system work around the precast panels and designed the system to allow for removals to help facilitate the constriction process.

The shoring was constructed next to an existing church sensitive to movements. Excavation procedures were modified and extra considerations were taken in both the design and construction to reduce any movements and vibrations. Further, RWH completed target, inclinometer and vibration monitoring to verify the shoring performance throughout construction and ensure minimal impact to the church structure.

Client: The Tricar Group

Location: London, Ontario

Aligning with the HCM group’s core value of sustainability, the Azure project became the first LEEDS condominium project in London’s history.

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
The Bow

The Bow

The future Bow building, located in Calgary, Alberta Canada, is an innovation in both architectural and shoring design. At 58 stories and with a footprint of two city blocks, The
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More