Skip to content

University of Toronto Faculty of Law

TTC Steels Launch Shaft

The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading required an upgrade to the capacity of the building foundation. HCM proposed an innovative solution to install micropiles next to the caissons to accommodate the additional loading. The micropile foundation was designed by RWH Engineering Inc. (RWH), an HC Group company.

Specialty equipment was required to install the micropiles inside the existing building, as there was only four meters of headroom in some areas. HCM used a low head room drill to install micropiles to depths of 18 meters. The micropile design required triple post-grouting to achieve the necessary bond between the grout and the soil. The soil encountered was comprised of layers of sand, silt, and clay. To confirm the design adhesion, a sacrificial load test was performed to 250% of the ULS load.

This project is an example of how HCM/RWH can offer alternative foundation solutions to meet the needs of any project, including projects with challenging site restrictions.

Client: Eastern Construction

Location: Toronto, Ontario

Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More