Skip to content

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during the excavation for a new retaining wall at the Eglinton LRT project. The 14m (45’) high slope was approximately halfway excavated for a permanent block retaining wall when it a sudden slip failure occurred creating concern for the adjacent properties. RWH designed a slope retention system with soil nails and shotcrete facing to remediate the slope and allow for continued excavation. Using a TEI drill mounted on an excavator, HCM was able to reach the top of slope to install soil nails.  Shotcrete was applied by a nozzleman in an elevated work platform. Once the exposed portion of the failed slope was stabilized, excavation was able to resume and HCM continued installing additional lifts of anchors and shotcrete to the base of the finished slope for a total protected area of 1250m2 (13,500 SF).

HCM and RWH provided an efficient solution, adapting the slope protection design to assist with the durability of the permanent retaining wall. Real-time design changes were made onsite to accommodate additional area required after installation had already commenced, enabling the original retaining wall construction to resume as fast as possible. 

 

Location: Toronto, ON

Customer: Metrolinx

LRT Slope Protection at Retaining Wall
LRT Slope Protection at Retaining Wall
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More