Skip to content

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during the excavation for a new retaining wall at the Eglinton LRT project. The 14m (45’) high slope was approximately halfway excavated for a permanent block retaining wall when it a sudden slip failure occurred creating concern for the adjacent properties. RWH designed a slope retention system with soil nails and shotcrete facing to remediate the slope and allow for continued excavation. Using a TEI drill mounted on an excavator, HCM was able to reach the top of slope to install soil nails.  Shotcrete was applied by a nozzleman in an elevated work platform. Once the exposed portion of the failed slope was stabilized, excavation was able to resume and HCM continued installing additional lifts of anchors and shotcrete to the base of the finished slope for a total protected area of 1250m2 (13,500 SF).

HCM and RWH provided an efficient solution, adapting the slope protection design to assist with the durability of the permanent retaining wall. Real-time design changes were made onsite to accommodate additional area required after installation had already commenced, enabling the original retaining wall construction to resume as fast as possible. 

 

Location: Toronto, ON

Customer: Metrolinx

LRT Slope Protection at Retaining Wall
LRT Slope Protection at Retaining Wall
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More