Skip to content

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during the excavation for a new retaining wall at the Eglinton LRT project. The 14m (45’) high slope was approximately halfway excavated for a permanent block retaining wall when it a sudden slip failure occurred creating concern for the adjacent properties. RWH designed a slope retention system with soil nails and shotcrete facing to remediate the slope and allow for continued excavation. Using a TEI drill mounted on an excavator, HCM was able to reach the top of slope to install soil nails.  Shotcrete was applied by a nozzleman in an elevated work platform. Once the exposed portion of the failed slope was stabilized, excavation was able to resume and HCM continued installing additional lifts of anchors and shotcrete to the base of the finished slope for a total protected area of 1250m2 (13,500 SF).

HCM and RWH provided an efficient solution, adapting the slope protection design to assist with the durability of the permanent retaining wall. Real-time design changes were made onsite to accommodate additional area required after installation had already commenced, enabling the original retaining wall construction to resume as fast as possible. 

 

Location: Toronto, ON

Customer: Metrolinx

LRT Slope Protection at Retaining Wall
LRT Slope Protection at Retaining Wall
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More
Paruk Residence

Paruk Residence

Overcoming Poor Soil-Bearing Capacity The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River.
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More