Skip to content

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions

The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized shoring contractor that will take on many challenges relating to foundation design.

On this particular project, HCM took on the tasks of:

  • shotcrete shoring
  • caissons
  • micropiles
  • excavation
  • site services
  • demolition with the constraints of limited access and project complexity.

A portion of the work was to be performed indoors, which required special care towards the patients of the hospital and the HCM workers. The original design for this inside work included conventional pad footings dowelled in to existing caissons five feet below the finished floor. The soil conditions are unique on this project due to the fact that the site is situated at the bottom of the Niagara Escarpment where bedrock is on an incline. This increased the depth required for adequate bearing stratum, requiring the entire area to be excavated and the perimeter shored. To save costs to all parties involved, HCM proposed an alternate to the original design to provide hand-dug caisson caps around the existing caisson and column construction. Caissons were excavated to depths of 18 feet below the finished floor using reinforced compression rings and shotcrete shoring to reach adequate bedrock.

The above innovations were the optimal solution for this portion of work resulting in another successful hospital project by HCM on budget, on time.

Client: PCL
Location: Hamilton, Ontario

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More

University of Toronto Faculty of Law

TTC Steels Launch Shaft The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading
Read More