Skip to content

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions

The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized shoring contractor that will take on many challenges relating to foundation design.

On this particular project, HCM took on the tasks of:

  • shotcrete shoring
  • caissons
  • micropiles
  • excavation
  • site services
  • demolition with the constraints of limited access and project complexity.

A portion of the work was to be performed indoors, which required special care towards the patients of the hospital and the HCM workers. The original design for this inside work included conventional pad footings dowelled in to existing caissons five feet below the finished floor. The soil conditions are unique on this project due to the fact that the site is situated at the bottom of the Niagara Escarpment where bedrock is on an incline. This increased the depth required for adequate bearing stratum, requiring the entire area to be excavated and the perimeter shored. To save costs to all parties involved, HCM proposed an alternate to the original design to provide hand-dug caisson caps around the existing caisson and column construction. Caissons were excavated to depths of 18 feet below the finished floor using reinforced compression rings and shotcrete shoring to reach adequate bedrock.

The above innovations were the optimal solution for this portion of work resulting in another successful hospital project by HCM on budget, on time.

Client: PCL
Location: Hamilton, Ontario

HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More

Talbot Street

Talbot Street HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More

University of Toronto Faculty of Law

TTC Steels Launch Shaft The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading
Read More