Skip to content

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions

The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized shoring contractor that will take on many challenges relating to foundation design.

On this particular project, HCM took on the tasks of:

  • shotcrete shoring
  • caissons
  • micropiles
  • excavation
  • site services
  • demolition with the constraints of limited access and project complexity.

A portion of the work was to be performed indoors, which required special care towards the patients of the hospital and the HCM workers. The original design for this inside work included conventional pad footings dowelled in to existing caissons five feet below the finished floor. The soil conditions are unique on this project due to the fact that the site is situated at the bottom of the Niagara Escarpment where bedrock is on an incline. This increased the depth required for adequate bearing stratum, requiring the entire area to be excavated and the perimeter shored. To save costs to all parties involved, HCM proposed an alternate to the original design to provide hand-dug caisson caps around the existing caisson and column construction. Caissons were excavated to depths of 18 feet below the finished floor using reinforced compression rings and shotcrete shoring to reach adequate bedrock.

The above innovations were the optimal solution for this portion of work resulting in another successful hospital project by HCM on budget, on time.

Client: PCL
Location: Hamilton, Ontario

Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More