The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM) was contracted by the Crosslinx group to perform segmental excavation method (SEM) and support of excavation (SOE) below the existing subway tunnel. HCM performed the detailed excavation and the installation of dry mix shotcrete in 6 galleries for the phased installation of structural needle beams to support the tunnel above.
HCM’s SEM work involved excavation in 1.1m sections, installation and stressing of temporary supports, and installation of accelerated fibre-reinforced dry mix shotcrete for the walls and base slab. Due to strict movement tolerances of the tunnel above, a unique prestressed waler incorporated with shotcrete shoring was implemented. Special design and constructability considerations were coordinated with the designer to ensure safety during excavation. HCM installed a waler and tie-rod system that was prestressed from between the walers to achieve the deformed shape required by designers.
Due to HCM’s knowledge and experience with shotcrete and associated applications,
this unique project was executed successfully and to the satisfaction of the project
team.

Location: Toronto, ON 

Customer: SKYGRiD Construction Inc.

Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More
HC Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More

University of Toronto Faculty of Law

TTC Steels Launch Shaft The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More