This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in Toronto.

  • Micro piles were used to support a cantilever canopy on one level and HC Matcon completed the full excavation, shoring and footings as a package to the owner.
  • The shoring design called for over sized MAI bars due to low corrosive soil, and a 100 year plus life is expected.
  • The house construction is wood framed which was a lower cost than steel/concrete in that hillside loads over time are taken by the shoring system, which is 150 mm from the house walls.
  • The advantages of shotcrete shoring include smaller equipment to access and do the nails, as typical shoring solution involved large equipment and high costs to build working berms on a hillside lot.

Owners of land that was typically considered unsuitable as building lots can re consider and realize hidden value with permanent soil nail walls constructed by HC Matcon. HCM is a full service Design Build Specialist contractor.

Client: HC Matcon
Location: Toronto, Ontario

Grand House

Grand House

Difficult But Not Impossible The Grand House is a student designed and constructed co-operative housing project located in Cambridge, Ontario.  It has won awards and is a landmark building. Due
Read More

McMaster Nuclear Building

McMaster Nuclear Building The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of
Read More
Currie Reservoir

Currie Reservoir

Horizontal Underpinning This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary.