HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing plant location in Tillsonburg, ON.

As the project was located in an existing, active manufacturing facility, extra care had to be taken on the part of HC Matcon to work within the confines of the building space, which included tight egress for our equipment and limited head room clearance (20′+/-).

Safety is always a number one priority, but additional attention had to be paid as the work was being completed within an active plant with live personnel maintaining scheduled productions.

Some unforeseen obstructions were encountered during helical installation, but with quick decision making and our crews efficiency, HC Matcon was able to complete the project on time and on budget.

Client: Grassmere Construction
Location: Tillsonburg, Ontario

Maxwell Bates

Maxwell Bates This project, located on Fourth Street in the downtown core of Calgary, consisted of a tied-back continuous caisson wall.  The caisson wall provided zero ground loss and minimal
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More