Skip to content

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization

The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive in Toronto, Ontario.

HC Matcon was procured to install 39 helical piles using ECP square shaft helicals with a 8-10-12 inch helix configuration in lieu of the equivalent 1.5” square bar (SS150).  Upon HC Matcon’s arrival on site, current ground conditions had changed as the existing slope was unstable and eroded creating a challenging work site.  The slope was found to be 5 degrees steeper than expected and posed a problem to the stability of the excavators and to the installation of the helicals.  HC Matcon stabilized the excavator on the slope to allow for a flexible control for the hydraulic motor to allow the required vertical helical        installation angle under the roadway.  The final problem encountered was the alignment of the helical pile with the hydraulic motor which was resolved with minor adjustments to the equipment.  HC Matcon installed all 39 helicals at their 30 degree inclination to depths ranging between 36 and 45 feet and preloaded all helicals to 90 KN on oversized steel bearing pads.

This project reveals that HC Matcon is able to adapt to develop systems that allow for proper mobility and stability of the installation equipment.  While HC Matcon did start later than scheduled, all problems were overcome and the schedule was still completed on time.  Today, the slope is covered with natural vegetation and is performing as intended.

Client: NEI Construction Corp.

Location: 421 Parkside Dr., Toronto, Ontario

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More