Skip to content

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization

The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive in Toronto, Ontario.

HC Matcon was procured to install 39 helical piles using ECP square shaft helicals with a 8-10-12 inch helix configuration in lieu of the equivalent 1.5” square bar (SS150).  Upon HC Matcon’s arrival on site, current ground conditions had changed as the existing slope was unstable and eroded creating a challenging work site.  The slope was found to be 5 degrees steeper than expected and posed a problem to the stability of the excavators and to the installation of the helicals.  HC Matcon stabilized the excavator on the slope to allow for a flexible control for the hydraulic motor to allow the required vertical helical        installation angle under the roadway.  The final problem encountered was the alignment of the helical pile with the hydraulic motor which was resolved with minor adjustments to the equipment.  HC Matcon installed all 39 helicals at their 30 degree inclination to depths ranging between 36 and 45 feet and preloaded all helicals to 90 KN on oversized steel bearing pads.

This project reveals that HC Matcon is able to adapt to develop systems that allow for proper mobility and stability of the installation equipment.  While HC Matcon did start later than scheduled, all problems were overcome and the schedule was still completed on time.  Today, the slope is covered with natural vegetation and is performing as intended.

Client: NEI Construction Corp.

Location: 421 Parkside Dr., Toronto, Ontario

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More