Skip to content

8 Ida Street

8 Ida Street

HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack of real-estate and property, the home owners decided to build an in ground pool inside of their newly completed residence.  The residence consisted of an existing crawl space in which the pool was requested.  It should be noted that the interior finishes consisted of sensitive glass and marble which were sensitive to movement below.

The project involved deepening the crawl space for the swimming pool addition.  Innovation was required due to a unique underpinning design which included two layers of continuous rebar within the panel in order for it to be used as a permanent foundation wall.  This created constructability issues due to the required three panel sequences of installation.  To allow for unobstructed panel excavation, HC Matcon and RWH, an HC Group company, special bulkhead steel embedments were fabricated from mesh and anchor couplers (provided by Williams Form Engineering) in the HC Matcon shop. These were used in place of rebar to allow for all threading of the bars satisfying the engineer.

The work was successfully completed on time and on budget.  Underpinning systems are a specialty of HC Matcon.

Client: Laureden Inc.

Location: Toronto, Ontario

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More

Twinning Tunnels

Twinning Tunnels The installation of a deep trunk sanitary sewer system in the bedrock beneath Erin Mills Parkway in Mississauga required an innovative approach for shoring manholes. For this project,
Read More
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM)
Read More