Skip to content

Aldershot GO Station Improvements

Our Innovative Solution Saves Time

Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The project was further complicated by the proximity of high speed passenger train rails and the need to maintain and operate the facility while the work was in progress.

  • In order to minimize the impact of the installation of the shoring, HC Matcon Inc. opted to install a single row of multi-strand high capacity tie backs; in excess of 900 KN capacities.
  • The high design loads required these anchors installed under strict on site quality control of strand and grouting procedures.

The innovative approach taken by HC Matcon Inc’s design team provided the optimum solution to the strict requirements of the project while, significantly reducing the duration and subsequent impact to the overall project completion schedule.

Client: Kenaidian Contracting
Location: Burlington, Ontario

Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
St. Joseph's Healthcare Redevelopment Project

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized
Read More
Currie Reservoir

Currie Reservoir

Horizontal Underpinning This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary.
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More