Skip to content

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions

The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized shoring contractor that will take on many challenges relating to foundation design.

On this particular project, HCM took on the tasks of:

  • shotcrete shoring
  • caissons
  • micropiles
  • excavation
  • site services
  • demolition with the constraints of limited access and project complexity.

A portion of the work was to be performed indoors, which required special care towards the patients of the hospital and the HCM workers. The original design for this inside work included conventional pad footings dowelled in to existing caissons five feet below the finished floor. The soil conditions are unique on this project due to the fact that the site is situated at the bottom of the Niagara Escarpment where bedrock is on an incline. This increased the depth required for adequate bearing stratum, requiring the entire area to be excavated and the perimeter shored. To save costs to all parties involved, HCM proposed an alternate to the original design to provide hand-dug caisson caps around the existing caisson and column construction. Caissons were excavated to depths of 18 feet below the finished floor using reinforced compression rings and shotcrete shoring to reach adequate bedrock.

The above innovations were the optimal solution for this portion of work resulting in another successful hospital project by HCM on budget, on time.

Client: PCL
Location: Hamilton, Ontario

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More