Skip to content

Spray River Bridge

Spray River Bridge

During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As the bridge was located on a non-motorized pathway in Banff National Park – 10km from the nearest road – the project required a solution that took into account the remote location. 

The existing bridge was able to be reused, but required a new alignment and redesigned footings.  RWH worked in conjunction with Parks Canada to design a piling solution for the new foundation.  A major consideration was designing for future scour depths and therefore pipe micropiles were selected. The design included eight micropiles, each extending 12m deep. The equipment was trammed to the location using existing fire roads and a cable tram was used to access the far side as protection of the surrounding natural environment was a key priority on this project. 

HCM’s versatile team worked together to handle this small, yet challenging job and successfully met the client’s unique project requirements.

Client: Parks Canada

Location: Banff National Park, Alberta

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More