Skip to content

Slope Remediation

Slope Remediation

HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario.

Prior to HCM’s involvement, the site was excavated 7m into a silty clay at a 1:1 slope.  HCM was contacted after the slope began to fail and large movements were seen.  After RWH completed the design solution, HCM worked from a boom lift to install anchors with a TEI drill mounted on an excavator to stabilize the slope.  HCM applied meshed shotcrete directly to the face of the slope and tied in the system by post-tensioning the anchors.  Utilizing real-time engineering and quick execution, HCM was able to complete the installation without substantial ground loss, allowing for work onsite to be conducted safely.

HCM has applied shotcrete with tieback anchors as slope protection systems on many job sites with poor soils or tight sloping constraints. This project is an example of HCM’s and RWH’s ability to act quickly and adapt to changing site conditions to provide effective solutions.

Location: Coruuna, ON

Customer: Cope Construction and Contracting Inc.

Slope Remediation
Slope Remediation
Slope Remediation
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Currie Reservoir

Currie Reservoir

Horizontal Underpinning This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary.
Read More

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More