Skip to content

Slope Remediation

Slope Remediation

HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario.

Prior to HCM’s involvement, the site was excavated 7m into a silty clay at a 1:1 slope.  HCM was contacted after the slope began to fail and large movements were seen.  After RWH completed the design solution, HCM worked from a boom lift to install anchors with a TEI drill mounted on an excavator to stabilize the slope.  HCM applied meshed shotcrete directly to the face of the slope and tied in the system by post-tensioning the anchors.  Utilizing real-time engineering and quick execution, HCM was able to complete the installation without substantial ground loss, allowing for work onsite to be conducted safely.

HCM has applied shotcrete with tieback anchors as slope protection systems on many job sites with poor soils or tight sloping constraints. This project is an example of HCM’s and RWH’s ability to act quickly and adapt to changing site conditions to provide effective solutions.

Location: Coruuna, ON

Customer: Cope Construction and Contracting Inc.

Slope Remediation
Slope Remediation
Slope Remediation
Bluwater Condominiums

Bluwater Condominiums

The Pemberton Group is adding the luxury waterfront Bluwater Condominiums to its portfolio. The 22,000 SF area of shoring area will accommodate the construction of three eight-story buildings on the
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More