Skip to content

Slope Remediation

Slope Remediation

HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario.

Prior to HCM’s involvement, the site was excavated 7m into a silty clay at a 1:1 slope.  HCM was contacted after the slope began to fail and large movements were seen.  After RWH completed the design solution, HCM worked from a boom lift to install anchors with a TEI drill mounted on an excavator to stabilize the slope.  HCM applied meshed shotcrete directly to the face of the slope and tied in the system by post-tensioning the anchors.  Utilizing real-time engineering and quick execution, HCM was able to complete the installation without substantial ground loss, allowing for work onsite to be conducted safely.

HCM has applied shotcrete with tieback anchors as slope protection systems on many job sites with poor soils or tight sloping constraints. This project is an example of HCM’s and RWH’s ability to act quickly and adapt to changing site conditions to provide effective solutions.

Location: Coruuna, ON

Customer: Cope Construction and Contracting Inc.

Slope Remediation
Slope Remediation
Slope Remediation
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More