Skip to content

Slope Remediation

Slope Remediation

HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario.

Prior to HCM’s involvement, the site was excavated 7m into a silty clay at a 1:1 slope.  HCM was contacted after the slope began to fail and large movements were seen.  After RWH completed the design solution, HCM worked from a boom lift to install anchors with a TEI drill mounted on an excavator to stabilize the slope.  HCM applied meshed shotcrete directly to the face of the slope and tied in the system by post-tensioning the anchors.  Utilizing real-time engineering and quick execution, HCM was able to complete the installation without substantial ground loss, allowing for work onsite to be conducted safely.

HCM has applied shotcrete with tieback anchors as slope protection systems on many job sites with poor soils or tight sloping constraints. This project is an example of HCM’s and RWH’s ability to act quickly and adapt to changing site conditions to provide effective solutions.

Location: Coruuna, ON

Customer: Cope Construction and Contracting Inc.

Slope Remediation
Slope Remediation
Slope Remediation
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More