Skip to content

Slope Remediation

Slope Remediation

HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario.

Prior to HCM’s involvement, the site was excavated 7m into a silty clay at a 1:1 slope.  HCM was contacted after the slope began to fail and large movements were seen.  After RWH completed the design solution, HCM worked from a boom lift to install anchors with a TEI drill mounted on an excavator to stabilize the slope.  HCM applied meshed shotcrete directly to the face of the slope and tied in the system by post-tensioning the anchors.  Utilizing real-time engineering and quick execution, HCM was able to complete the installation without substantial ground loss, allowing for work onsite to be conducted safely.

HCM has applied shotcrete with tieback anchors as slope protection systems on many job sites with poor soils or tight sloping constraints. This project is an example of HCM’s and RWH’s ability to act quickly and adapt to changing site conditions to provide effective solutions.

Location: Coruuna, ON

Customer: Cope Construction and Contracting Inc.

Slope Remediation
Slope Remediation
Slope Remediation
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More

University of Toronto Faculty of Law

TTC Steels Launch Shaft The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More