Skip to content

Pixel by Battistella

Pixel by Battistella

HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was located at 1037 Second Avenue N. W. Calgary, Alberta. HCM, in conjunction with RWH Engineering, designed, supplied and installed a tied-back continuous caisson wall.

The shoring was designed for a maximum excavation depth of 10 meters below grade for a total of approximately 18,900 square feet of shoring area. The soil conditions consisted of gravels with the presence of ground water, making the continuous caisson wall the superior solution due to the zero ground loss and minimal water infiltration advantages.

This project had strict timeline requirements and called for the shoring to be completed in 28 days. In order to finish the project on time, HCM had to use double shifts and injection anchors to double the anchor production. The steps taken by HCM were successful and the project was finished within the given deadline.

Client: Battistella Developments

Location: Calgary, Alberta

Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More

Odeon Ronmore Development

Odeon Ronmore Development HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More