Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts and storm and sewer pipe in downtown Barrie, Ontario.

  • Helical pile support systems were ideal for use on the project based on the type of soils encountered and the project location related to the nearby lake. Excavation parameters were further impeded by the proximity of streets and roads required to be in operation while the work was in progress. 50 Kip design capacities were achieved on small diameter pipe, (2-7/8) which were installed and torqued as required.
  • The versatility of the installations enabled the Owner to minimize costs by installing only lengths and depths required.
  • Due to the nature and achievable installation production rate it was possible to stay ahead of the concrete work as small areas of work were excavated in sections.

The helical pile supports were utilized on both the Kidd’s Creek project as well as the second phase of the retrofit and expansion located at Toronto and Simcoe Streets in Barrie, Ontario.

Client: Drainstar Contracting Ltd
Location: Barrie, Ontario

The Bow

The Bow

The future Bow building, located in Calgary, Alberta Canada, is an innovation in both architectural and shoring design. At 58 stories and with a footprint of two city blocks, The
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More

Talbot Street

Talbot Street HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was