Centron Business Park Retaining Wall

Steep Slope Retaining Wall

The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast Calgary, Alberta. The purpose of the permanent wall was to support a portion of 4th Street S.E. which is serving as an access road to a multi-building complex for commercial real estate. The retaining wall was designed by EBA Engineering Consultants Ltd. as a Cantilever Tangent Wall with various excavation depths, c/w embedment of soldier piles between 7.5m and 14.5m below-grade. The length of shoring wall was 142 linear metres with a total of 470 square metres of exposed surface area. The pile sizes included diameters of 810mm and 912mm. The overall scope of work consisted of drilling approximately 70 soldier piles and 140 filler piles. The client also accepted HCM’s proposal to trim the front surface of the 10 MPa concrete wall which then became more suitable for future application of architectural cladding or finished shotcrete. HCM completed this task with an excavator-mounted Antraquip wall trimmer.

The design also required precision in the placing of the piles along the contour of a curvilinear access road which, in most cases, took place on the edge of a steep slope.

HCM Contractors successfully completed this project to the engineer’s satisfaction, and on schedule.

Client: Centron Group of Companies
Location: Calgary, Alberta

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More