Aldershot GO Station Improvements

Our Innovative Solution Saves Time

Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The project was further complicated by the proximity of high speed passenger train rails and the need to maintain and operate the facility while the work was in progress.

  • In order to minimize the impact of the installation of the shoring, HC Matcon Inc. opted to install a single row of multi-strand high capacity tie backs; in excess of 900 KN capacities.
  • The high design loads required these anchors installed under strict on site quality control of strand and grouting procedures.

The innovative approach taken by HC Matcon Inc’s design team provided the optimum solution to the strict requirements of the project while, significantly reducing the duration and subsequent impact to the overall project completion schedule.

Client: Kenaidian Contracting
Location: Burlington, Ontario

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More