Wal-Mart Micropiles

Overcoming Poorly Engineered Fill

This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill.

  • The previous winter had frozen some of the fill, and footing settlements of up to 3 inches were on-going as the steel was erected.
  • HC Matcon mobilized a Design Build solution utilizing 60 Ft. long micro piles, with special connections to the already designed footings and piers. Sacrificial steel design was used to provide low cost micro piles.
  • HC Matcon worked 7 days per week for 3 weeks to install 192 piles.

The Walmart store opened on schedule and was a technical success. HC Matcon is innovative when problems occur, working with owners and General Contractors to find the most economical solution.

Client: Buttcon Ltd
Location: Rexdale, Ontario

Currie Barracks Residential Development

Currie Barracks Residential Development HCM was contracted to provide the design and installation of shoring system for a multi-family condo development in the Currie Barracks area SW Calgary. Conventional cantilever
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
St. Joseph's Healthcare Redevelopment Project

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More