Overcoming Poor Soil-Bearing Capacity

The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River. A geotechnical investigation performed by Patriot Engineering revealed very poor soil bearing capacity, unsuitable for a slab-on-grade or strip footing foundation.

  • The floor slab was designed as a structural slab supported on grade beams resting on helical pier foundations. The helical piers were 2-7/8 inch diameter, 55 ksi minimum yield strength, galvanized, and supplied by Ideal Group.
  • The helical piers were designed for a maximum 30 kips working load, which was achieved at a torque resistance of approximately 9,000 ft. lbs. Using a 17,000 ft. lbs. McMillen drive unit, 94 piers were installed in 3 days.

HCM also did the excavation, perimeter shotcrete shoring and U/S stone placement c/w geotextile, which helped construction access and provided a clean surface for the concrete form work contractor.

Client: HC Matcon
Location: Toronto, Ontario

 

 

CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
HC Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More