Paruk Residence

Overcoming Poor Soil-Bearing Capacity

The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River. A geotechnical investigation performed by Patriot Engineering revealed very poor soil bearing capacity, unsuitable for a slab-on-grade or strip footing foundation.

  • The floor slab was designed as a structural slab supported on grade beams resting on helical pier foundations. The helical piers were 2-7/8 inch diameter, 55 ksi minimum yield strength, galvanized, and supplied by Ideal Group.
  • The helical piers were designed for a maximum 30 kips working load, which was achieved at a torque resistance of approximately 9,000 ft. lbs. Using a 17,000 ft. lbs. McMillen drive unit, 94 piers were installed in 3 days.

HCM also did the excavation, perimeter shotcrete shoring and U/S stone placement c/w geotextile, which helped construction access and provided a clean surface for the concrete form work contractor.

Client: HC Matcon
Location: Toronto, Ontario

 

 

Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More
Credit Valley Hospital

Credit Valley Hospital

Alternative to Save Time and Money The Credit Valley Hospital in Mississauga, Ontario is undergoing a massive expansion and renovation. HC Matcon was brought in to undertake the shoring, underpinning,
Read More
Bluwater Condominiums

Bluwater Condominiums

The Pemberton Group is adding the luxury waterfront Bluwater Condominiums to its portfolio. The 22,000 SF area of shoring area will accommodate the construction of three eight-story buildings on the
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More