Skip to content

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles

This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a caisson wall as well as horizontal shoring and underpinning.

  • The purpose of the installation of the caisson wall was to provide support for the existing pump-house structure as the excavation was taking place between the pump-house and underground water tank.
  • The retaining wall was designed by J.R. Spronken & Associates Ltd. as a Cantilever Secant Pile Wall with a maximum excavation depth of 8.0m below grade.
  • The length of the shoring wall is approximately 48 linear meters with total exposed surface area of about 370 square meters.
  • The pile sizes used include 760mm soldier piles and 610mm filler piles. The overall scope of the work consisted of drilling 28 soldier piles and 30 filler piles.

The client also approached HCM with the request to provide horizontal shoring/underpinning at the bottom of the excavation in order to provide a safe working platform for the connection of a 900mm diameter pipe between the pump-house and water tank. HCM completed this task by pushing a series of H-piles horizontally, using a hydraulic jack which was set-up on a specially designed steel frame system attached to the caisson wall.

HCM Contractors completed this project ahead of schedule and to the complete satisfaction of both the client and the engineer.

Client: PCL Construction Management
Location: Calgary, Alberta

TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More
Telus Sky tower - HC Matcon

Telus Sky tower

Telus Sky tower The Telus Sky tower will be the 3rd tallest building in Calgary with the deepest basement excavation in western Canada. HCM Group took on the challenge of
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More