Skip to content

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles

This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a caisson wall as well as horizontal shoring and underpinning.

  • The purpose of the installation of the caisson wall was to provide support for the existing pump-house structure as the excavation was taking place between the pump-house and underground water tank.
  • The retaining wall was designed by J.R. Spronken & Associates Ltd. as a Cantilever Secant Pile Wall with a maximum excavation depth of 8.0m below grade.
  • The length of the shoring wall is approximately 48 linear meters with total exposed surface area of about 370 square meters.
  • The pile sizes used include 760mm soldier piles and 610mm filler piles. The overall scope of the work consisted of drilling 28 soldier piles and 30 filler piles.

The client also approached HCM with the request to provide horizontal shoring/underpinning at the bottom of the excavation in order to provide a safe working platform for the connection of a 900mm diameter pipe between the pump-house and water tank. HCM completed this task by pushing a series of H-piles horizontally, using a hydraulic jack which was set-up on a specially designed steel frame system attached to the caisson wall.

HCM Contractors completed this project ahead of schedule and to the complete satisfaction of both the client and the engineer.

Client: PCL Construction Management
Location: Calgary, Alberta

Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More