Skip to content

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles

This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a caisson wall as well as horizontal shoring and underpinning.

  • The purpose of the installation of the caisson wall was to provide support for the existing pump-house structure as the excavation was taking place between the pump-house and underground water tank.
  • The retaining wall was designed by J.R. Spronken & Associates Ltd. as a Cantilever Secant Pile Wall with a maximum excavation depth of 8.0m below grade.
  • The length of the shoring wall is approximately 48 linear meters with total exposed surface area of about 370 square meters.
  • The pile sizes used include 760mm soldier piles and 610mm filler piles. The overall scope of the work consisted of drilling 28 soldier piles and 30 filler piles.

The client also approached HCM with the request to provide horizontal shoring/underpinning at the bottom of the excavation in order to provide a safe working platform for the connection of a 900mm diameter pipe between the pump-house and water tank. HCM completed this task by pushing a series of H-piles horizontally, using a hydraulic jack which was set-up on a specially designed steel frame system attached to the caisson wall.

HCM Contractors completed this project ahead of schedule and to the complete satisfaction of both the client and the engineer.

Client: PCL Construction Management
Location: Calgary, Alberta

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
Currie Reservoir

Currie Reservoir

Horizontal Underpinning This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary.
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More