Skip to content

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles

This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a caisson wall as well as horizontal shoring and underpinning.

  • The purpose of the installation of the caisson wall was to provide support for the existing pump-house structure as the excavation was taking place between the pump-house and underground water tank.
  • The retaining wall was designed by J.R. Spronken & Associates Ltd. as a Cantilever Secant Pile Wall with a maximum excavation depth of 8.0m below grade.
  • The length of the shoring wall is approximately 48 linear meters with total exposed surface area of about 370 square meters.
  • The pile sizes used include 760mm soldier piles and 610mm filler piles. The overall scope of the work consisted of drilling 28 soldier piles and 30 filler piles.

The client also approached HCM with the request to provide horizontal shoring/underpinning at the bottom of the excavation in order to provide a safe working platform for the connection of a 900mm diameter pipe between the pump-house and water tank. HCM completed this task by pushing a series of H-piles horizontally, using a hydraulic jack which was set-up on a specially designed steel frame system attached to the caisson wall.

HCM Contractors completed this project ahead of schedule and to the complete satisfaction of both the client and the engineer.

Client: PCL Construction Management
Location: Calgary, Alberta

Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More