Skip to content

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles

This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a caisson wall as well as horizontal shoring and underpinning.

  • The purpose of the installation of the caisson wall was to provide support for the existing pump-house structure as the excavation was taking place between the pump-house and underground water tank.
  • The retaining wall was designed by J.R. Spronken & Associates Ltd. as a Cantilever Secant Pile Wall with a maximum excavation depth of 8.0m below grade.
  • The length of the shoring wall is approximately 48 linear meters with total exposed surface area of about 370 square meters.
  • The pile sizes used include 760mm soldier piles and 610mm filler piles. The overall scope of the work consisted of drilling 28 soldier piles and 30 filler piles.

The client also approached HCM with the request to provide horizontal shoring/underpinning at the bottom of the excavation in order to provide a safe working platform for the connection of a 900mm diameter pipe between the pump-house and water tank. HCM completed this task by pushing a series of H-piles horizontally, using a hydraulic jack which was set-up on a specially designed steel frame system attached to the caisson wall.

HCM Contractors completed this project ahead of schedule and to the complete satisfaction of both the client and the engineer.

Client: PCL Construction Management
Location: Calgary, Alberta

Lakeview Water Treatment Plant

Lakeview Water Treatment Plant This project was part of the second phase of an expansion program to the region of Peel’s Lakeview Water Treatment Plant. Given the information provided at
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More