Milton Grade Separation
Client: BOT Construction
Location: Milton, Ontario
This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a caisson wall as well as horizontal shoring and underpinning.
The client also approached HCM with the request to provide horizontal shoring/underpinning at the bottom of the excavation in order to provide a safe working platform for the connection of a 900mm diameter pipe between the pump-house and water tank. HCM completed this task by pushing a series of H-piles horizontally, using a hydraulic jack which was set-up on a specially designed steel frame system attached to the caisson wall.
HCM Contractors completed this project ahead of schedule and to the complete satisfaction of both the client and the engineer.
Client: PCL Construction Management
Location: Calgary, Alberta
This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary. The interlocking secant pile wall (caisson wall) allows for an accelerated construction schedule as it eliminates the ground loss that is present with the use of other styles of shoring. Where utilities were present, bracing supports were used to resist the lateral pressures present behind the filler piles.
Unique to this job was the installation of horizontal underpinning. The job required a new connection between the existing reservoir and pump house. To accomplish this task, a tunnel had to be created to accommodate the 900mm connecting water pipe. The underpinning provides support for the tunnel walls. The system worked well; after excavation, the resulting tunnel allowed safe access for the installation of the connection pipe to the pump house.
Because of the job’s proximity to the working water reservoir, special environmental precautions had to be taken in order to avoid contamination. Site-specific procedures were implemented; in instances where lubricating oils had to be used, for example when sliding the horizontal underpinning beams, food grade oils were used over hydrocarbon-based oils. As a result, the integrity of the water supply was maintained throughout the duration of the project.
Client: PCL
Location: Calgary, Alberta
Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
HC Matcon’s scope of work, includes:
HC Matcon will work with all parties involved in a project to ensure a swift execution with minimal conflicts.
Client: B. Gottardo
Location: Toronto, Ontario
The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized shoring contractor that will take on many challenges relating to foundation design.
On this particular project, HCM took on the tasks of:
A portion of the work was to be performed indoors, which required special care towards the patients of the hospital and the HCM workers. The original design for this inside work included conventional pad footings dowelled in to existing caissons five feet below the finished floor. The soil conditions are unique on this project due to the fact that the site is situated at the bottom of the Niagara Escarpment where bedrock is on an incline. This increased the depth required for adequate bearing stratum, requiring the entire area to be excavated and the perimeter shored. To save costs to all parties involved, HCM proposed an alternate to the original design to provide hand-dug caisson caps around the existing caisson and column construction. Caissons were excavated to depths of 18 feet below the finished floor using reinforced compression rings and shotcrete shoring to reach adequate bedrock.
The above innovations were the optimal solution for this portion of work resulting in another successful hospital project by HCM on budget, on time.
Client: PCL
Location: Hamilton, Ontario
The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.
HC Matcon’s scope of work included:
At various points during construction, HC Matcon has been required to provide innovative design-build solutions to accommodate changes to the original design.
Client: EllisDon
Location: Scarborough, Ontario
The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast Calgary, Alberta. The purpose of the permanent wall was to support a portion of 4th Street S.E. which is serving as an access road to a multi-building complex for commercial real estate. The retaining wall was designed by EBA Engineering Consultants Ltd. as a Cantilever Tangent Wall with various excavation depths, c/w embedment of soldier piles between 7.5m and 14.5m below-grade. The length of shoring wall was 142 linear metres with a total of 470 square metres of exposed surface area. The pile sizes included diameters of 810mm and 912mm. The overall scope of work consisted of drilling approximately 70 soldier piles and 140 filler piles. The client also accepted HCM’s proposal to trim the front surface of the 10 MPa concrete wall which then became more suitable for future application of architectural cladding or finished shotcrete. HCM completed this task with an excavator-mounted Antraquip wall trimmer.
The design also required precision in the placing of the piles along the contour of a curvilinear access road which, in most cases, took place on the edge of a steep slope.
HCM Contractors successfully completed this project to the engineer’s satisfaction, and on schedule.
Client: Centron Group of Companies
Location: Calgary, Alberta