The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by KO Constructors to design, supply, and install several shoring systems as well as deep foundations.  

The project scope consisted of two shoring walls spanning a total distance of 2.6 km, ranging from 4.5 to 14 meters in depth. The shoring walls consisted of both bypass shotcrete and caisson wall to provide railway protection and allow for continuous GO train service. Precise coordination between all parties was required when drilling as close as 100 mm to the operational tracks.

HCM worked closely with the general contractor and owner to meet strict scheduling goals. HCM employed up to 5 large diameter drill rigs at one time, performed night work, and readily adapted to changes in the shoring scope to allow for early excavation and structure installation. RWH Engineering Inc. (RWH), an HC Group company, performed the precision monitoring on the project and was also involved in the design process, enabling accelerated design changes.

The Weston Tunnel project is an example of the service HCM and RWH can provide to a large scale project where schedule goals are important.  The HC Group is able to develop solutions and adapt to any changes in conditions allowing the project to progress without delays.

Client: KO Constructors

Location: Toronto, Ontario

Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More
Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of