Weston Road

Weston Road

The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by KO Constructors to design, supply, and install several shoring systems as well as deep foundations.  

The project scope consisted of two shoring walls spanning a total distance of 2.6 km, ranging from 4.5 to 14 meters in depth. The shoring walls consisted of both bypass shotcrete and caisson wall to provide railway protection and allow for continuous GO train service. Precise coordination between all parties was required when drilling as close as 100 mm to the operational tracks.

HCM worked closely with the general contractor and owner to meet strict scheduling goals. HCM employed up to 5 large diameter drill rigs at one time, performed night work, and readily adapted to changes in the shoring scope to allow for early excavation and structure installation. RWH Engineering Inc. (RWH), an HC Group company, performed the precision monitoring on the project and was also involved in the design process, enabling accelerated design changes.

The Weston Tunnel project is an example of the service HCM and RWH can provide to a large scale project where schedule goals are important.  The HC Group is able to develop solutions and adapt to any changes in conditions allowing the project to progress without delays.

Client: KO Constructors

Location: Toronto, Ontario

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More
Great Lakes Copper Plant

Great Lakes Copper Plant

Great Lakes Copper Plant The Great Lakes Copper Plant in London, Ontario, posed a technical challenge in shotcrete shoring. HC Matcon helped to facilitate the installation of a new copper
Read More

Talbot Street

Talbot Street HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More