The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by KO Constructors to design, supply, and install several shoring systems as well as deep foundations.  

The project scope consisted of two shoring walls spanning a total distance of 2.6 km, ranging from 4.5 to 14 meters in depth. The shoring walls consisted of both bypass shotcrete and caisson wall to provide railway protection and allow for continuous GO train service. Precise coordination between all parties was required when drilling as close as 100 mm to the operational tracks.

HCM worked closely with the general contractor and owner to meet strict scheduling goals. HCM employed up to 5 large diameter drill rigs at one time, performed night work, and readily adapted to changes in the shoring scope to allow for early excavation and structure installation. RWH Engineering Inc. (RWH), an HC Group company, performed the precision monitoring on the project and was also involved in the design process, enabling accelerated design changes.

The Weston Tunnel project is an example of the service HCM and RWH can provide to a large scale project where schedule goals are important.  The HC Group is able to develop solutions and adapt to any changes in conditions allowing the project to progress without delays.

Client: KO Constructors

Location: Toronto, Ontario

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More