Mapleview Drive

Mapleview Drive

The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH Engineering Inc. (RWH), an HC Group company, engaged the design responsibility for the project, resulting in significant improvements to the tendered drawings. HCM and RWH redesigned the shoring system to better suit excavation and bridge footing construction. The redesign revised the center pier shoring system from a boxed in strutted system to a tieback shoring system. This allowed better access for shoring installation, excavation, and forming.

Due to site conditions and steep slopes, HCM coordinated all drilling platforms with the GC which optimized shoring and excavation activities and maintained the project schedule. Coordination with the GC for the temporary bridge placement was paramount as track removal and temporary bridge and track installation had to occur in a time period of four days.

 

Client: Arnott Construction Ltd.

Location: Barrie, Ontario

Significant time-saving was realized during installation by redesigninig the tendered sheet piling and driven piles close to existing tracks with an extended drilled double pile and lagging.

The work was successfully completed on time and on budget. This project exemplifies HCM’s ability to find cost-effective solutions to complex project requirements.

TTC Patten Building

TTC Patten Building HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets
Read More

Midtown Lofts

Midtown Lofts On this project, HCM in conjunction with RWH Engineering Inc. (RWH), provided the owner with a complete design-build package and precision monitoring services for an 8.5m deep temporary
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley