HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was located at 1037 Second Avenue N. W. Calgary, Alberta. HCM, in conjunction with RWH Engineering, designed, supplied and installed a tied-back continuous caisson wall.

The shoring was designed for a maximum excavation depth of 10 meters below grade for a total of approximately 18,900 square feet of shoring area. The soil conditions consisted of gravels with the presence of ground water, making the continuous caisson wall the superior solution due to the zero ground loss and minimal water infiltration advantages.

This project had strict timeline requirements and called for the shoring to be completed in 28 days. In order to finish the project on time, HCM had to use double shifts and injection anchors to double the anchor production. The steps taken by HCM were successful and the project was finished within the given deadline.

Client: Battistella Developments

Location: Calgary, Alberta

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM)
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More