HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was located at 1037 Second Avenue N. W. Calgary, Alberta. HCM, in conjunction with RWH Engineering, designed, supplied and installed a tied-back continuous caisson wall.

The shoring was designed for a maximum excavation depth of 10 meters below grade for a total of approximately 18,900 square feet of shoring area. The soil conditions consisted of gravels with the presence of ground water, making the continuous caisson wall the superior solution due to the zero ground loss and minimal water infiltration advantages.

This project had strict timeline requirements and called for the shoring to be completed in 28 days. In order to finish the project on time, HCM had to use double shifts and injection anchors to double the anchor production. The steps taken by HCM were successful and the project was finished within the given deadline.

Client: Battistella Developments

Location: Calgary, Alberta

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More
EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More
Telus Sky tower - HC Matcon

Telus Sky tower

Telus Sky tower The Telus Sky tower will be the 3rd tallest building in Calgary with the deepest basement excavation in western Canada. HCM Group took on the challenge of
Read More