HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was located at 1037 Second Avenue N. W. Calgary, Alberta. HCM, in conjunction with RWH Engineering, designed, supplied and installed a tied-back continuous caisson wall.

The shoring was designed for a maximum excavation depth of 10 meters below grade for a total of approximately 18,900 square feet of shoring area. The soil conditions consisted of gravels with the presence of ground water, making the continuous caisson wall the superior solution due to the zero ground loss and minimal water infiltration advantages.

This project had strict timeline requirements and called for the shoring to be completed in 28 days. In order to finish the project on time, HCM had to use double shifts and injection anchors to double the anchor production. The steps taken by HCM were successful and the project was finished within the given deadline.

Client: Battistella Developments

Location: Calgary, Alberta

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More